 |
SUPPORT OF EXCAVATION adjacent to the
river, through 20-feet of soil, and 20-feet of rock, system consisted of
secant piles, tieback, rock bolts, and shotcrete (contractor's design, not
ours). We did borings, packer tests, and assisted GC. |
|
 |
Sheeting & Shoring design for the
new York County PA, Judicial Center (Courthouse), we used PYWALL to design
the soldier piles and tiebacks. |
 |
UNDERPINNING/SUPPORT OF EXCAVATION Using
soil nails and shotcrete, and existing wireless Telecommunications HUB
building was underpinned 14-feet to allow for expansion |
|
 |
Foundation modification existing tower in
downtown Savannah Georgia, the challenge in this situation was to transfer
load from leg to the new foundation, bypassing the overstressed anchor
bolts. We worked very closely with Williams Form Engineering who
provided pigtail anchors and huge eye bolts |
|
 |
National Park Service, Fort Washington
Here we used ground penetrating radar to scan the sides of the century old
masonry to detect water damage. |
 |
Tie Down or Rock Anchor proof testing in
the middle of nowhere, in the middle of winter. |
 |
Non Destructive Analysis of 1908 factory
- Here we used radar to locate the "Kahn Method of Reinforced
Concrete", then cored the floor, extracted samples, and had the yield
strength determined. This was done in an operating candy bar factory. |
 |
In-Situ or Pressure Meter Testing for a
parking garage in downtown Baltimore (Little Italy) - Here we used the
pressure meter testing to validate to get much higher drilled shaft skin
friction values than normal correlation to SPT would predict. |
|
 |
Retaining Wall Analysis - This was
20 to 30 year old wall of unknown design or origin that was failing. |
 |
Stealth Tower - The existing (1950) tower
was eventually surrounded by urban sprawl and it became advisable to
construct a stealth tower. |
| |
|
 |
Light Pole Survey- A major mall owner had
a series of light pole (50-ft) failures resulting is substantial property
damage, but miracously, no injuries. Using a DM4-DL ultrasonic
thickness gage with data logger, we survey 60 poles, getting 60+ reading per
pole, and then compiled a risk analysis spreadsheet of the 4000 data points. |
| |
|
 |
Cantilevered sheet pile cofferdam
(picture was taken before excavation), using PYWALL |
| |
|
 |
Routine geotechnical explorations in
support of new mausoleum construction. |